Risk management allows the project manager and the project team not to(71).
(71)A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
參考譯文
下面不屬于風(fēng)險(xiǎn)管理中項(xiàng)目經(jīng)理和項(xiàng)目團(tuán)隊(duì)職責(zé)的是 (71) 。
A.排除大部分項(xiàng)目執(zhí)行中的風(fēng)險(xiǎn)
B.風(fēng)險(xiǎn)識(shí)別
C.風(fēng)險(xiǎn)分析
D.妥善處理
參考答案
(71)A
The project life-cycle can be described as(72).
(72)A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
參考譯文
關(guān)于項(xiàng)目周期劃分正確的是 (72) 。
A.啟動(dòng)、計(jì)劃、執(zhí)行、收尾
B.計(jì)劃、授權(quán)、報(bào)告
C.計(jì)劃、控制、方案設(shè)計(jì)、WBS的發(fā)展、終止
D.啟動(dòng)、執(zhí)行、報(bào)告
參考答案
(72)A
(73)is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.
(73)A.PERT
B.AOA
C.WBS
D.PDM
參考譯文
(73) 用于關(guān)鍵路徑法,是用于編制項(xiàng)目進(jìn)度網(wǎng)絡(luò)圖的一種方法,它使用方框或者長(zhǎng)方形(被稱作節(jié)點(diǎn))代表活動(dòng),它們之間用箭頭連接,顯示彼此之間存在的邏輯關(guān)系。
A.PERT
B.AOA
C.WBS
D.PDM
參考答案
(73)D
Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.